Guidelines for the use of reference books of basic prices. II

MINISTRY OF REGIONAL DEVELOPMENT
RUSSIAN FEDERATION

ORDER


In accordance with the Regulations on the Ministry of Regional Development of the Russian Federation, approved by Decree of the Government of the Russian Federation of January 26, 2005 N 40 (Collected Legislation of the Russian Federation, 2005, N 5, Art. 390; N 13, Art. 1169; 2006, N 6, 712; N 18, art. 2002; 2007, N 45, art. 5488; 2008, N 22, art. 2582; N 42, art. 378; N 6, art. 738; N 14, art. pricing in the field of urban planning" (registered by the Ministry of Justice of the Russian Federation on May 12, 2008, registration N 11661; Bulletin of normative acts of federal executive bodies, 2008, N 22) and by order of the Ministry of Regional Development of the Russian Federation of August 20, 2009 N 353 "On approval qualification of estimated standards to be applied when determining the estimated cost of capital construction projects, the construction of which is financed with the involvement of federal budget funds" (registered by the Ministry of Justice of the Russian Federation on 02.10.2009, registration N 14940; Bulletin of normative acts of federal executive bodies, 2009, N 42)

I order:

1. Approve as a state estimate standard the attached Guidelines for the use of reference books of basic prices for design work in construction.

2. The Department for Regulation of Urban Development (I.V. Ponomarev), within 10 days from the date of signing, send this order for state registration to the Ministry of Justice of the Russian Federation.

3. The control of the execution of this order shall be entrusted to the Deputy Minister of Regional Development of the Russian Federation S.I. Kruglik.

Acting Minister
V.A.Tokarev

Registered
at the Ministry of Justice
Russian Federation
March 23, 2010
registration N 16686

Guidelines for the use of reference books of basic prices for design work in construction

Application

I. Fundamentals

1.1. Guidelines for the use of reference books of basic prices for design work in construction (hereinafter referred to as the Guidelines) are intended to determine the cost of developing design and working documentation for the construction of new buildings and structures, their reconstruction, expansion and technical re-equipment (hereinafter referred to as the construction of facilities), determined from using reference books of basic prices for design work in construction.

1.2. The provisions given in the Guidelines apply to all reference books of base prices for design work in construction (hereinafter referred to as the Reference Books) entered in the federal register of estimated standards to be used when determining the estimated cost of capital construction projects as state estimated standards.

1.3. When using the Handbooks, the following should be taken into account:

1.3.1. The base prices of the Reference books are set depending on the natural indicators of the design objects (capacity, length, capacity, area, etc.) or on the total cost of construction.

1.3.2. The prices given in the Handbooks are set in accordance with the composition and requirements for the content of sections of project documentation for the construction of enterprises, buildings, structures, provided for by Decree of the Government of the Russian Federation of February 16, 2008 N 87 "On the composition of sections of project documentation and requirements for their content" (Sobraniye zakonodatelstva Rossiyskoy Federatsii, 2008, N 8, art. 744).

1.3.3. The Handbooks provide prices for individual design of capital construction objects of buildings and structures using drawings of standard (reusable) products and assemblies for individual elements of building structures.

1.3.4. The prices of the Guides take into account the costs of developing design and working documentation, which are attributable without value added tax.

1.3.5. The prices of the Handbooks include the following works and services:

1.3.5.1. Production of demonstration materials (except for demonstration layouts).

1.3.5.2. Participation of the design organization together with the customer in coordinating the finished project documentation with state bodies and local governments.

1.3.5.3. Protection of project documentation in expert and approving instances.

1.3.6. The prices of the Handbooks for the development of design and working documentation do not include the costs of:

1.3.6.1. Development of the design solutions specified in the design assignment in several versions, with the exception of variant studies to select the optimal design solutions.

1.3.6.2. Development of solutions for the monumental and decorative design of enterprises, buildings and structures.

1.3.6.3. Making changes to the design and working documentation (with the exception of correcting errors made by the design organization).

1.3.6.4. Development of detailed drawings of metal structures (KMD) and industrial pipelines of factory production.

1.3.6.5. Carrying out surveys and measuring work at facilities subject to reconstruction, expansion and technical re-equipment.

1.3.6.6. Development of design documentation for custom-made equipment, in addition to the preparation of initial requirements for the design of this equipment.

1.3.6.7. Business trips. The base prices of the Guides do not take into account the costs of business trips, including the costs of administrative personnel, if the business trips of this personnel are directly related to the design of the facility.

1.3.6.8. Development of projects for the production of works (PPR).

1.3.6.9. Development of working documentation for the construction of temporary buildings and structures for the needs of construction organizations.

1.3.6.11. Research and experimental work.

1.3.6.12. Development of automated enterprise management systems (APCS) and automated process control systems (APCS).

1.3.6.13. Development of the section "Measures for civil defense and measures to prevent natural and man-made emergencies". The base price for the development of the specified section is determined by the relevant Directory.

1.3.6.14. Performance of work on the assessment of the impact of the capital construction object on the environment (EIA).

1.4. The distribution of the base price for the development of design and working documentation is carried out, as a rule, in accordance with the indicators given in Table 1, and can be specified by agreement between the contractor and the customer.

Table 1.

Table 1

Types of documentation

Percentage of base price

Project documentation

working documentation

1.5. If the design assignment provides for the simultaneous development of design documentation and partial development of working documentation, then the total percentage of the base price is determined by agreement between the construction customer and the design organization, depending on the architectural, functional, technological, structural and engineering solutions contained in the design documentation, as well as their level of detail.

1.6. When performing design work in a reduced composition of sections and volumes of work, as opposed to those provided for by the current regulatory documents, their price, regardless of the methods of its calculation, is determined by the prices for the development of design and working documentation using a reduction factor, the amount of which is set by the contractor in agreement with the customer, in accordance with the laboriousness of work and the relative cost of developing sections of design and working documentation.

1.7. When determining the initial (maximum) price of the contract for the performance of design work to their value determined at the time of the competition (auction), it is recommended to use the deflator index established by the Ministry of Economic Development of Russia in accordance with clause 5 of the Rules for developing a forecast for the socio-economic development of the Russian Federation, approved by Decree of the Government of the Russian Federation of July 22, 2009 N 596 (Collection of Legislation of the Russian Federation, 2009, N 30, Art. 3833), effective in the middle of the regulatory design period.

1.8. When applying the Handbooks, it should be taken into account that the Handbooks present the recommended relative costs for the development of sections of design and working documentation (as a percentage of the base price), which can be specified for subdivisions (departments) of the design organization when designing a specific facility within a certain total design cost, depending on the complexity of the work performed.

II. The procedure for using reference books when determining base prices for design work

2.1. The procedure for determining the base price depending on the natural indicators of design objects.

2.1.1. The base price for the development of design and working documentation is determined by the formula:

C = (a + bx) x K,

Where:

a and b - constant values ​​for a certain interval of the main indicator of the designed object in thousand rubles;

x - the main indicator of the designed object;

K - coefficient reflecting inflationary processes in the design at the time of determining the price of design work for the construction of the facility.

2.1.2. When applying the Handbooks, it should be taken into account that the prices of the Handbooks for the development of design and working documentation for enterprises, workshops, buildings and structures take into account the cost of designing all on-site engineering networks, communications, structures and devices (electricity supply, water supply, sewerage, heat supply, etc.), including connection workshops, buildings and structures for them, as well as a scheme for the planning organization of a land plot (master plan and landscaping) within the construction site.

If the price in the Directory is set for the development of design and working documentation for the main production (excluding auxiliary, as well as site engineering networks and structures), the total design cost is determined by a set of cost indicators for designing the main and auxiliary facilities.

The cost of designing capital construction projects does not take into account the cost of designing engineering networks and communications outside the construction site.

2.1.3. If the projected object has a value of the main indicator less than the minimum or more than the maximum indicator given in the price tables of the Handbooks, the price for the development of design and working documentation is determined by extrapolation in accordance with the formula given in Appendixes No. 1 and 2 to these Guidelines. This provision also applies to positions when in the price table before the minimum and after the maximum indicator there are, respectively, the words "before" and "above". In cases where the accepted indicator is less than half of the minimum or more than twice the maximum indicator given in the table, the base price of design work is determined in the manner prescribed by paragraph 2.1.4 of these Guidelines.

2.1.4. The price for the development of design and working documentation for the construction of facilities for which prices are not given in the Handbooks and cannot be accepted by analogy is determined by calculating the cost in accordance with the cost calculation (Form 3P).

2.2. The procedure for determining the base price of the total cost of construction.

2.2.1. The base price for the development of design and working documentation is determined from the total cost of construction of the entire complex of buildings (structures) or an object, determined according to the summary estimate calculation of the cost of construction, depending on the categories of complexity of design objects.

2.2.2. The cost of construction can be determined:

- with the use of analogue objects, taking into account their comparability;

- according to aggregated indicators of the estimated cost per 1 sq.m of total area, 1 cubic meter of building volume, 1 m (km) of the route, 1 hectare of building, per unit of power, productivity, etc.;

- by types or complexes of works.

2.2.3. The price for the development of design and working documentation is determined according to the tables of the Handbooks corresponding to the functional purpose of capital construction projects.

2.2.4. The base price of project documentation is determined by the formula:

C - base price of design and working documentation in current prices;

C - base price of design and working documentation as of 01.01.2001;

- cost of construction as of 01.01.2001;

- percentage of the base price of the total cost of construction in 2001 prices (table of the Directory);

K - coefficient reflecting inflationary processes in the design at the time of determining the price of design work.

To recalculate the cost of construction of objects from the price level as of 01/01/2000 to the price level as of 01/01/2001, a coefficient equal to 1.25 is taken.

2.2.5. When the projected object has a construction cost value that is between the indicators given in the table, the base price for the development of project documentation is determined by interpolation. If the cost of building an object is less or more than the extreme cost indicators given in the price table, the base price of the design work is accepted in the amounts established for the extreme indicators without extrapolation in the direction of decrease or increase.

2.2.6. In the event that the volume of construction and installation work on the construction site is less than 60% of the total cost of construction, the following coefficients are applied to the prices for design work:

up to 50% - 0.95;

up to 40% - 0.9;

up to 30% - 0.8;

up to 20% - 0.7.

2.2.7. If the contract for the performance of design work provides for the possibility of clarifying the cost of design, then such clarification is recommended to be carried out based on the cost of construction determined as a result of the design.

2.2.8. When determining the base price, coefficients that take into account complicating factors (clauses 3.3, 3.7 and 3.8 of these Guidelines) are not applied.

III. The procedure for determining the cost of design work, taking into account additional factors affecting the complexity of design

3.1. The price for the development of design and working documentation using the mock-up design method is determined at the prices of the Handbooks using multiplying factors. If there are no established multipliers in the Handbooks, the price for the development of project documentation by the specified method is determined by applying the coefficients to the base price: project documentation - 1.05; working documentation - 1.1.

3.2. The binding price of standard or reusable design documentation, without making changes to the above-ground part of the building, is determined by the prices of the Reference Books using coefficients from 0.2 to 0.35. In this case, the minimum size of the coefficient is accepted when linking the object without making any changes to the aboveground and underground parts of the building. The price of binding standard or reusable design documentation with changes to it in the underground and aboveground parts is determined at the prices of the Reference Books using a general coefficient of up to 0.8, depending on the complexity of the work. The approximate scope of work on the development of individual elements of buildings and structures as a percentage of the design cost is given in Appendix No. 3 to these Guidelines.

3.3. The price for the development of design and working documentation for the construction of unique objects is determined at the prices of the Directories using a multiplying factor of up to 1.5, with the exception of the Directories, which establish a special procedure for calculating the price of these objects.

3.4. The price for the development of design and working documentation for the reconstruction of existing enterprises, workshops, buildings and structures is determined at the prices of Reference books of basic prices for design work for construction.

At the same time, when determining the cost of design work based on the value of the main physical indicator of the designed object, which should be achieved as a result of its reconstruction, technical re-equipment, - applying a coefficient of up to 1.5 to the prices of the Reference books. When determining the cost of design work from the cost of reconstruction - up to 1.3.

For especially dangerous, technically complex and unique capital construction projects - up to 2.0 and 1.7, respectively.

The size of the coefficient is set by the design organization in agreement with the customer.

3.5. The price for the development of design (working) documentation for the overhaul of facilities is determined according to the relevant reference books of basic prices.

3.6. When compiling local estimates using the resource method, in the absence of a centralized data bank on the current cost of resources in the construction region, a multiplying factor of 1.1 is applied to the cost of developing estimate documentation.

3.7. The price for the development of design and working documentation for the construction of enterprises, buildings and structures in difficult conditions is determined at the prices of the Reference books, applying the following coefficients to the cost of design work, for the development of which special requirements are established by the relevant regulatory documents:

Factors complicating design

Odds

Permafrost, subsidence, swelling soils; karst and landslide phenomena; location of the construction site above mine workings, in flooded areas, etc.

Seismicity 7 points

Seismicity 8 points

Seismicity 9 points

If there are two or more complicating factors, coefficients are applied for each factor.

3.8. The price of designing enterprises, buildings and structures with the installation of imported main technological equipment used by the design organization for the first time is determined by the prices of the Reference Books; at the same time, a coefficient of up to 1.3 is applied to the cost of types of design work, the development of which is complicated due to the use of the specified equipment, as agreed with the customer.

3.9. The costs of design organizations related to their performance of the functions of the general designer and supervision of design work transferred to subcontracts are determined in the amount of up to 2% of the price for the development of design and working documentation transferred to subcontracted design organizations, and are paid additionally.

3.10. The prices of the Handbooks take into account the cost of 4 copies of design and working documentation transferred to the customer. The cost of copies of design products issued at the request of the customer in excess of the specified quantity is determined in addition to the base price.

3.11. When determining the base design price according to the Reference books of basic prices for design work for construction, in the event of a reduction, at the request of the customer, established in the design assignment, design time compared to the standard, it is recommended to apply the following multiplying factors:

while shortening the term

in more times

3.12. Price application guidelines and correction factors given in one Handbook are not allowed to be used when determining the cost of design work according to other Handbooks.

3.13. The price for the development of design and working documentation for the construction of facilities abroad is determined taking into account complicating factors:

Complicating factors

Ratios to development cost

project documentation

working documentation

Translation of text materials of technical documentation, inscriptions on drawings into a foreign language

Translation of materials of a foreign customer into Russian

Double checking of calculations, drawings and specifications, calculations of the scope of work, estimate documentation and other design materials, making duplicate copies of cripples, increased requirements for the design and packaging of project documentation

Other factors affecting the increase in the complexity of design work:

Current frequency and voltage, the difference in the permissible range of fluctuations in current frequency, different from the Russian Federation (to the cost of designing electrical equipment, power supply, low currents, and, if necessary, other sections)

Dry or humid tropical climate

When the design organization first uses equipment and materials purchased in the customer's countries or supplied from other countries (according to clause 3.8 of these Guidelines)

Application of foreign norms and standards for materials and equipment, performance of structural calculations on them, etc., specified by the customer in the design assignment

Additional requirements for design and working documentation for the construction of facilities on a contract basis, including the preparation of specifications for equipment and materials for temporary import

Note. Increasing coefficients are applied to the cost of sections of project documentation or parts thereof, the development of which becomes more complicated.

3.14. When determining the cost of design work at the prices of the Reference Books, in the presence of several complicating factors and, in connection with this, several coefficients greater than one are used, the total multiplying coefficient is determined by summing their fractional parts and one. When determining the cost of design work using several coefficients less than one, the overall reduction coefficient is determined by multiplying them.

When determining the cost of design work at the prices of the Reference Books, the pricing coefficients are multiplied. The pricing factors include the distribution coefficients of the base price for the development of design and working documentation, types of capital construction objects, reconstruction, as well as the coefficients established in the Reference books of basic prices for design work for construction.

3.15. Costs of design organizations located in areas where, in accordance with applicable law, payments are made due to regional regulation of wages, incl. payments according to district coefficients, as well as wage bonuses for continuous work experience and other benefits provided for by legislation in the regions of the Far North and areas equivalent to them, are additionally determined by introducing multiplying coefficients to the base price total, established on the basis of the relevant substantiating calculations performed by the design organization itself.

Appendix N 1. Extrapolation and interpolation when calculating the price of design work

Appendix No. 1
to the Guidelines


In the case when the projected object has a value of the main indicator less than the minimum or more than the maximum indicator given in the table of the Base Price Directory, the base price of the design is determined by extrapolation; at the same time, the value of the adjustment to the price is reduced by 40%, i.e. in the calculation, the indicator of the projected object X is taken with a coefficient of 0.6.

If the power indicator of the object is less than the tabular indicator, the base price of its design is determined by the formula:

Where:

a, c - constant values ​​taken according to the table of the minimum value of the indicator;





If the power indicator of the object is greater than the tabular indicator, the base price of its design is determined by the formula:

C \u003d a + in x (0.4 x X + 0.6 x X),

Where:

a, c - constant values ​​taken according to the table of the maximum value of the indicator;



X - indicator of the designed object.

In the case when only the value of a is given in the table, and the projected object has an indicator value that does not match those given in the table, the base price of its design is determined by interpolation or extrapolation; when extrapolating upwards or downwards, the value of the correction to the price is reduced by 40% (when calculating the value of the correction, a reduction factor K = 0.6 is introduced).

Appendix N 2. Examples of determining the base price for designing objects whose indicators are higher, lower or are between the indicators given in the reference tables

Appendix No. 2
to the Guidelines

_______________
Table indicators are accepted conditionally.

Example 1. In the case when the table of the Reference book of basic prices contains the values ​​a and c.

Sewage sludge incineration facilities with capacity, thousand m3/year: from 25 to 60

1 thousand m / year

1.1. It is required to determine the base price for the design of sewage sludge incineration facilities with a capacity of 15 thousand m3/year. The base price is determined by the formula:

Where:

a and b are constant values ​​taken according to the table of the minimum value of the indicator;

X - the minimum indicator given in the table;



Calculation example:

66.5 + 1.2 x (0.4 x 25 + 0.6 x 15) = 89.3 thousand rubles

1.2. It is required to determine the base price for the design of sewage sludge incineration facilities with a capacity of 80 thousand m3/year. The base price is determined by the formula:

C \u003d a + in x (0.4 x X + 0.6 x X),

Where:

a and b are constant values ​​taken according to the table of the maximum value of the indicator;

X - the maximum indicator given in the table;

X is a given indicator of the designed object.

Calculation example:

66.5 + 1.2 x (0.4 x 60 + 0.6 x 80) = 152.9 thousand rubles


Example 2. In the case when only the value a.

In the Reference book of basic prices for design work, a table is given:

Name of the design object

Unit of measurement of the main indicator of the object

Constant values ​​of the base price for the development of design and working documentation, thousand rubles.

Wash water treatment facilities, capacity, m/day

………………..

………………..

2.1. It is required to determine the base price for designing a wash water treatment plant with a capacity of 100 m/day.

Calculation example:

2.2. It is required to determine the base price for designing a wash water treatment facility with a capacity of 300 m/day.

Calculation example:

2.3. It is required to determine the base price for designing a wash water treatment plant with a capacity of 90,000 m/day.

Calculation example:

Appendix N 3. Approximate scope of work on the development of individual elements of buildings and structures when using standard and reusable projects

Appendix No. 3
to the Guidelines

(as a percentage of the cost of designing the building as a whole)

Name of individual elements of buildings and structures

Interest

I. Underground part of the building

Foundations, other than pile foundations, with resizing

Foundations, except for pile foundations, with a change in type

Pile foundations

II. Aboveground part

Facades without processing of the heating project

Walls with a change in material, or thickness, or design

Floors with a change in the design, type or layout of panels

Redevelopment of premises

Floors with redesign

Interior decoration

Staircase and elevator assembly with a change in the design of the elevator

Redesigned roof



Electronic text of the document
prepared by CJSC "Kodeks" and verified according to.

General guidelines for the use of CBC dated 2002-08-10

GENERAL INSTRUCTIONS

FOR THE APPLICATION OF BASIC PRICE HANDBOOKS FOR DESIGN WORKS FOR CONSTRUCTION

Introduction date 2002-08-10

DEVELOPED BY FSUE "TSENTRINVESTproekt" of Gosstroy of Russia.

APPROVED by the Decree of the Gosstroy of Russia dated 07.08.02 N 102.

INTRODUCED AND PREPARED FOR APPROVAL by the Department of Pricing and Estimated Rationing in Construction and Housing and Communal Complex of Gosstroy of Russia.

ENTERED INTO EFFECT on August 10, 2002 by the Decree of the Gosstroy of Russia dated 07.08.02 N 102.

INTRODUCTION

Reference books of basic prices for design work for construction (hereinafter referred to as the Reference Books) are intended to determine basic prices for the purpose of subsequent formation of contractual prices for the development of project documentation for new construction, expansion, reconstruction and technical re-equipment of industrial and civil housing facilities.

General instructions are obligatory for application when using the prices for design work given in all Directories.

I. GENERAL INSTRUCTIONS FOR THE APPLICATION OF BASE PRICE HANDBOOKS FOR PROJECT

WORKS FOR CONSTRUCTION

1. The directories are intended for use by organizations of various organizational and legal forms that, in accordance with the legislation of the Russian Federation, have the status of a legal entity.

2. Base prices in the Directories are set depending on the natural indicators of design objects (capacity, length, capacity, area, etc.) and on the total cost of construction.

3. The prices given in the Handbooks are set in accordance with the composition, procedure for the development, approval and approval of project documentation for the construction of enterprises, buildings, structures, provided for by SNiP 11-01-95.

4. The Handbooks contain prices for individual design of new construction of facilities, buildings and structures, as well as individual elements of the complex using materials from standard and reusable economical individual projects of workshops, buildings and structures included in them, as well as drawings of standard building structures, products and units.

Prices include all costs for the development of project documentation and profit, excluding value added tax.

6. The prices of the Guides take into account and do not require additional payment for the following works and services:

6.1 production of demonstration materials (except for demonstration layouts);

6.2 participation of the design organization together with the customer in coordinating the finished project documentation with state bodies and local governments;

6.3 defense of the working draft (draft) in expert and approving authorities;

7. The complex prices of the Handbooks for the development of project documentation do not include the costs of:

7.1 development of the design solutions specified in the design assignment in several versions, with the exception of variant studies to select the optimal design solutions.

The development of additional options for a project, a working draft, or individual technological, structural, architectural and other solutions is established in the design assignment, which should also define the sections (or parts of these sections) of the project for which it is necessary to develop these options and the initial data necessary for them. development.

The degree of elaboration of additional options is established in agreement with the customer.

In the process of developing both the main and additional options, variant study of design solutions is carried out;

7.2 development of working drawings for special auxiliary structures, fixtures, devices and installations when designing facilities with particularly complex structures and work methods.

The base price for the development of working drawings of these structures, fixtures and devices is determined in the manner established by construction organizations, or by calculating the cost in accordance with costing;

7.3 development of solutions for the monumental and decorative design of enterprises, buildings and structures.

Such work, in cases where it is provided for by the design assignment, is carried out, as a rule, by organizations of the art fund under separate contracts and prices;

7.4 making changes to the project documentation (with the exception of correcting errors made by the design organization).

The performance of these works should be provided for by the assignment for the design of the facility or by a separate order of the customer and paid additionally;

7.5 development of detailed drawings of metal structures (KMD) and industrial pipelines of factory production.

The costs of the design organization that develops the KMD drawings on behalf of the customer are determined at the departmental prices of manufacturers or on the basis of costing and are paid additionally;

7.6. surveys and measurement works at facilities subject to reconstruction, expansion and technical re-equipment.

The cost of such work should be determined according to the relevant Handbooks, or by calculating the cost in accordance with the cost calculation;

7.7 development of design documentation for custom-made equipment, except for the preparation of initial requirements for the design of this equipment.

The base price guide takes into account the costs of preparing initial requirements for the development of design documentation for custom-made equipment, including single-piece and small-scale ones. The terms of reference for the specified equipment are developed by the manufacturer.

In some cases, when the development of the specified design documentation is entrusted to a design organization, it is carried out, as a rule, under contracts with the equipment manufacturer. If the manufacturer is not defined, then the development of design documentation for the equipment can be carried out by the design organization on behalf of the customer. At the same time, the base price for the performance of the specified design work is determined at the departmental rates of the manufacturers of the specified equipment;

7.8 business trips.

The basic prices of the Directory do not take into account the costs of business trips, including the costs of administrative personnel, if the business trips of this personnel are directly related to the design of the facility;

7.9 development of projects for the production of construction and installation works (PPR);

7.10 development of project documentation for the construction of temporary buildings and structures for the needs of construction organizations;

7.12 research and experimental work;

7.13 development of automated enterprise management systems (APCS) and automated process control systems (APCS).

The base price for the design of an automated control system and an automated process control system is determined according to the relevant price documents for the development of the specified technical documentation;

7.14 development of the section ITM Civil Defense and Emergency; the base price of development is determined by the relevant Directory;

7.15 development of the EIA section;

7.16 development of interiors, performed in accordance with GOST 21.507-81.

II. PROCEDURE FOR DETERMINING BASE PRICES FOR PROJECT WORKS

A. Depending on the natural indicators of design objects

1. The base price for the development of project documentation (project + working documentation) is determined by the formula:

Where

" " And " " - constant values ​​for a certain interval of the main indicator of the designed object, in thousand rubles;

The main indicator of the designed object;

A coefficient reflecting inflationary processes at the time of determining the price of design work for the construction of an object.

2. The prices of the Handbooks for the development of design documentation for enterprises, workshops, buildings and structures take into account the cost of designing all on-site engineering networks, communications, structures and devices (power supply, water supply, sewerage, heat supply, etc.), including the connection of workshops, buildings and structures to them , as well as the general plan and landscaping within the construction site. If the price in the Directory is set for the development of design documentation for the main production (excluding auxiliary, as well as site engineering networks and structures), a comprehensive assessment is carried out by a set of cost indicators for the design of main and auxiliary facilities.

The cost of designing off-site engineering networks and communications is not included in the complex prices and is determined additionally.

3. The price for the development of design documentation for individual workshops, buildings and structures, carried out by subcontracting design organizations, in cases where the cost of designing these facilities is taken into account by the prices of the corresponding Directory, is determined at the same prices at which the design cost was determined by the general designer.

4. If the projected object has a value of the main indicator less than the minimum or more than the maximum indicators given in the price tables of the Handbooks, the price for the development of project documentation is determined by extrapolation in accordance with the formula given in the appendix.

In cases where the accepted indicator is less than half of the minimum or more than twice the maximum indicator given in the table, the base price of design work is determined in the manner prescribed by clause 5.

5. The price for the development of design documentation for the construction of facilities for which prices are not given in the Handbooks and cannot be accepted by analogy, is determined by the cost calculation in accordance with the cost calculation.

6. The price for the development of project documentation for the reconstruction and technical re-equipment of existing enterprises, workshops, buildings and structures is determined at the prices of the Directories based on the value of the main indicator of the designed object, which should be achieved as a result of its reconstruction, technical re-equipment, using a coefficient of up to 1.5 set by the design organization in agreement with the customer.

7. The price for the development of technical documentation for the overhaul of building structures of buildings and structures is determined according to the relevant Base Price Directory.

If it is not possible to apply the specified Handbook, the price of works can be determined using the relevant Handbooks of basic prices for design work for new construction conditions, applying a reduction factor to the design price for new construction conditions in the amount of not more than 0.5, depending on the scope of work.

8. Costs of design organizations located in areas where, in accordance with the current legislation, payments are made due to the district regulation of wages, incl. payments according to district coefficients, as well as wage bonuses for continuous work experience and other benefits provided for by legislation in the regions of the Far North and areas equivalent to them, are additionally determined by introducing multiplying coefficients to the base price total, established on the basis of the relevant substantiating calculations performed by the design organization itself.

The method for calculating the multiplying factors is set out in the "Recommendations for determining the coefficient to the base prices for design work, taking into account the additional costs of organizations for preferential wage payments", approved and recommended for use by the letter of the Gosstroy of Russia dated 06/30/98 N 9-10-17 /40.

B. From the total cost of construction

9. The base price of project documentation (project + working documentation) is determined from the total cost of construction, depending on the categories of complexity of design objects.

10. The price of project documentation includes the cost of designing the entire complex of buildings, structures and types of design work, reflected in the total cost of construction, determined by an analogue object, taking into account their comparability or by aggregated indicators of estimated standards (per unit of indicators: 1 sq.m total area, 1 cubic meters building volume, 1 p.m tracks, 1 ha buildings, per unit of power, productivity, etc.).

11. The price of design documentation is determined according to the tables corresponding to the purpose of the design objects.

12. The base price of project documentation is determined by the formula:

Where

Base price of project documentation at current prices;

Base price of project documentation as of 01.01.2001;

- coefficient reflecting inflationary processes at the time of determining the price of design work for the construction of the facility.

To recalculate the cost of construction of objects from the price level as of 01/01/2000 to the price level as of 01/01/2001, a coefficient equal to 1.38 is taken.

13. In cases where the projected object has a construction cost value that is between the indicators given in the table, the base price for the development of project documentation is determined by interpolation.

If the cost of building an object is less or more than the extreme cost indicators given in the price table, the base price of design work is accepted in the amounts established for the extreme indicators (without extrapolation towards decrease or increase).

14. The price for the development of project documentation for the reconstruction and technical re-equipment of existing enterprises, workshops, buildings and structures is determined based on the cost of the reconstruction object, calculated for the conditions of the new construction of these facilities using a multiplying factor of up to 1.5 and a reducing factor that takes into account the amount of reconstruction work set by the design organization in agreement with the customer.

15. The distribution of the price of design work by design stages is given in the Handbooks and can be specified by agreement between the design organization and the customer.

16. The cost of individual sections of project documentation, taken into account by base prices, for new construction facilities is determined according to the tables of relative (estimated) cost given in the Handbooks and can be specified by the management of the design organization within the total cost for each stage of design, both when performing work on their own, and when transferring part of the work to subcontracting design organizations in agreement with them.

In the same manner, the relative cost of other sections of the design work, taken into account by base prices, but not highlighted in the relative cost tables, can be determined.

The relative cost of developing sections of design work during the reconstruction and technical re-equipment of existing enterprises, buildings and structures is established by the design organization within a certain total design cost, depending on the complexity of the work performed.

III. PROCEDURE FOR DETERMINING THE COST OF DESIGN WORKS, TAKING INTO ACCOUNT ADDITIONAL FACTORS AFFECTING THE LABOR OUTPUT OF DESIGN

1. The price for the development of design documentation using the mock-up design method is determined by the prices of the Reference books using multiplying factors.

In the absence of established multipliers in the Handbooks, the price for the development of project documentation by the specified method is determined by applying the coefficients to the base price: at the "project" stage - 1.05; at the stage of "working draft" and "working documentation" - 1.1.

2. The price of design work to be performed in a reduced composition and scope against that provided for by the current regulatory documents (development of additional project options or individual technological, structural, architectural and other solutions developed in accordance with the design assignment) is determined at prices for the development of design documentation of the corresponding object using a reduction factor, the size of which is set by the contractor in accordance with the complexity of the work as agreed with the customer.

3. When building in stages, the price for the development of working projects (projects) of enterprises and structures is determined by the prices of the Reference Books, based on the main indicators of each stage separately. At the same time, up to 20 percent of the cost of developing a working project (without working documentation) or a project of all subsequent stages is added to the cost of designing the first stage of construction.

4. The binding price of standard projects is determined by the prices of the Reference Books using a coefficient of 0.35.

The price of linking standard projects with the introduction of changes to them is determined by the prices of the Directories using a coefficient of up to 0.7, depending on the complexity of the work.

5. The price for the development of design documentation for the construction of facilities classified as unique and experimental in accordance with clause 8.4 of SNiP 10-01-94 "The system of regulatory documents in construction. Basic provisions" is determined by the prices of the Reference Books; at the same time, a coefficient of 1.5 is applied to the cost of those types of design work, the development of which becomes more complicated.

6. The price for the development of design documentation for the construction of enterprises, buildings and structures in difficult conditions is determined at the prices of the Directories, applying the following coefficients to the cost of design work, for the development of which special requirements are established by the relevant regulatory documents:

Factors complicating design

Odds

Permafrost, subsidence, swelling soils; karst and landslide phenomena; location of the construction site above mine workings, in flooded areas, etc.

1,15

Seismicity 7 points

1,15

Seismicity 8 points

1,20

Seismicity 9 points

1,30

If there are two or more complicating factors, coefficients are applied for each factor.

7. The price of designing enterprises, buildings and structures with the installation of imported main technological equipment used by the design organization for the first time is determined by the prices of the Reference Books; at the same time, a coefficient of up to 1.3 is applied to the cost of types of design work, the development of which is complicated due to the use of the specified equipment, as agreed with the customer.

8. The costs of design organizations related to the implementation of their functions as a general designer and supervision of design work transferred to subcontracts are determined in the amount of up to 2% of the price of development of project documentation transferred to subcontracted design organizations, and are paid additionally.

9. The prices of the Handbooks include the cost of 4 copies of project documentation issued to the customer.

The cost of copies of design products issued at the request of the customer in excess of the specified quantity is determined in addition to the base price.

10. When determining the cost of design work at the prices of the Reference Books, in the presence of several complicating factors and the application in connection with this of several coefficients greater than one, the total multiplying coefficient is determined by summing their fractional parts and one.

When determining the cost of design work using several coefficients less than one, the total reduction coefficient is determined by multiplying them.

11. Instructions on the application of prices and correction factors given in one Handbook are not allowed to be used when determining the cost of design work according to other Handbooks.

12. When determining the base price of design according to the Reference books of basic prices for design work for construction, in the event of a reduction in specific design time compared to the standard, in agreement with the customer, it is recommended to apply the following multiplying factors:

while shortening the term

1.2 times

Up to 1.1;

1.4 times

Up to 1.2;

2 or more times

Up to 1.4.

13. The price for the development of project documentation, carried out in accordance with the relevant regulatory documents governing the design of facilities for construction abroad, is determined in the following order.

The price for the implementation of justifications for investments in construction is determined by the prices for the development of projects using a coefficient of up to 0.5.

In cases when, during the development of justifications, a site (route) is selected for the construction of an enterprise, building, structure, the specified coefficient is increased by 0.05.

The price for the implementation of projects, working projects and working documentation for the new construction of enterprises, buildings and structures is determined at the prices of the Directories using, respectively, coefficients of 1.2; 1.04 and 1.

The price for the development of project documentation for the reconstruction and technical re-equipment of existing enterprises, buildings and structures is determined in the manner set forth in paragraphs 6 and 14 of Section II.

Additionally, coefficients are applied that take into account the influence of complicating factors:

N p / p

Complicating factors

Ratios to development cost

project

working documentation, working draft

Translation of text materials of technical documentation, inscriptions on drawings into a foreign language

1,05

Translation of materials of a foreign customer into Russian

1,03

1,03

Double checking of calculations, drawings and specifications, calculations of the scope of work, estimate documentation and other design materials, making duplicate copies of cripples, increased requirements for the design and packaging of project documentation

Other factors affecting the increase in the complexity of design work:

Current frequency and voltage, the difference in the allowable range of fluctuations in current frequency, other than RF (to the cost of designing electrical equipment, power supply, low currents, instrumentation and A, and, if necessary, other sections)

1,05

Dry or humid tropical climate

1,15

Development of project documentation, taking into account the use by the design organization for the first time of equipment and materials purchased in the customer's countries or supplied from third countries

Application of foreign norms and standards for materials and equipment, performance of structural calculations on them, etc., specified by the customer in the design assignment

1,15

Additional requirements for project documentation for the construction of facilities on a contract basis, including the preparation of specifications for equipment and materials for temporary import

Note.

Increasing coefficients are applied to the cost of sections of project documentation or parts thereof, the development of which becomes more complicated.

Application

Extrapolation and interpolation when calculating the price of design work

In the case when the projected object has a value of the main indicator less than the minimum or more than the maximum indicator given in the table of the Book of Prices or the Reference of Basic Prices, the base price of the design is determined by extrapolation; at the same time, the value of the adjustment to the price is reduced by 40%, i.e. in the calculation, the indicator of the designed object is taken with a coefficient of 0.6.

If the power indicator of the object is less than the tabular indicator, the base price of its design is determined by the formula:

Where

, - constant values ​​taken according to the table of the minimum value of the indicator;

- the minimum figure given in the table;

-

If the power indicator of the object is greater than the tabular indicator, the base price of its design is determined by the formula:

Where

, - constant values ​​taken according to the table of the maximum value of the indicator;

- the maximum figure given in the table;

- indicator of the designed object.

In the case when only the value "" is given in the table, and the projected object has an indicator value that does not match those given in the table, the base price of its design is determined by interpolation or extrapolation; when extrapolating in the direction of decreasing or increasing, the value of the correction to the price is reduced by 40% (when calculating the value of the correction, a reduction factor = 0.6 is introduced).

EXAMPLES OF DETERMINING THE BASIC PRICE OF THE DESIGN OF OBJECTS,

which are above, below or in between the indicators given in

Directory tables*

________________

* The indicators of the tables are taken conditionally.

In the Reference book of basic prices for design work, a table is given:

N p / p

Name of the design object

Unit of measurement of the main indicator of the object

Constant values ​​of the base price for the development of project documentation, thousand rubles rub.

Wastewater sludge incineration facilities with capacity, thousand m3/year:

from 25 to 60

1 thousand m / year

66,5

In the case when the values ​​\u200b\u200bof "" and "" are given in the table.

1. It is required to determine the base price for the design of sewage sludge incineration facilities with a capacity of 15 thousand m / year. The base price is determined by the formula:

"On Approval of Guidelines for the Application of Base Price Reference Books for Design Work in Construction"

Edition of 12/29/2009 - Valid from 04/30/2010

MINISTRY OF REGIONAL DEVELOPMENT OF THE RUSSIAN FEDERATION

ORDER
dated December 29, 2009 N 620

ON APPROVAL OF METHODOLOGICAL INSTRUCTIONS FOR THE APPLICATION OF DIRECTORIES OF BASIC PRICES FOR DESIGN WORKS IN CONSTRUCTION

1. Approve as a state estimate standard the attached Guidelines for the use of reference books of basic prices for design work in construction.

2. The Department for Regulation of Urban Development (I.V. Ponomarev), within 10 days from the date of signing, send this Order for state registration to the Ministry of Justice of the Russian Federation.

3. The control of the execution of this Order shall be entrusted to the Deputy Minister of Regional Development of the Russian Federation S.I. Kruglik.

And about. Minister
V.A.TOKAREV

APPROVED
Order of the Ministry
regional development
Russian Federation
dated December 29, 2009 No. 620

METHODOLOGICAL INSTRUCTIONS
ON THE APPLICATION OF DIRECTORIES OF BASIC PRICES FOR DESIGN WORKS IN CONSTRUCTION

I. GENERAL PROVISIONS

1.1. Guidelines for the use of reference books of basic prices for design work in construction (hereinafter referred to as the Guidelines) are intended to determine the cost of developing design and working documentation for the construction of new buildings and structures, their reconstruction, expansion and technical re-equipment (hereinafter referred to as the construction of facilities), determined from application of reference books of basic prices for design work in construction.

1.2. The provisions given in the Guidelines apply to all Reference books of basic prices for design work in construction (hereinafter referred to as the Reference books) entered in the federal register of estimated standards to be used when determining the estimated cost of capital construction projects as state estimated standards.

1.3. When using the Handbooks, the following should be taken into account:

1.3.1. The base prices of the Reference books are set depending on the natural indicators of the design objects (capacity, length, capacity, area, etc.) or on the total cost of construction.

1.3.2. The prices given in the Handbooks are set in accordance with the composition and requirements for the content of sections of project documentation for the construction of enterprises, buildings, structures, provided for by Decree of the Government of the Russian Federation of February 16, 2008 N 87 "On the composition of sections of project documentation and requirements for their content "(Collected Legislation of the Russian Federation, 2008, N 8, Art. 744).

1.3.3. The Handbooks provide prices for individual design of capital construction objects of buildings and structures using drawings of standard (reusable) products and assemblies for individual elements of building structures.

1.3.4. The prices in the Handbooks take into account the costs of developing design and working documentation, attributable without value added tax.

1.3.5. The prices of the Handbooks include the following works and services:

1.3.5.1. Production of demonstration materials (except for demonstration layouts).

1.3.5.2. Participation of the design organization together with the customer in coordinating the finished project documentation with state bodies and local governments.

1.3.5.3. Protection of project documentation in expert and approving instances.

1.3.6. The prices of the Handbooks for the development of design and working documentation do not include the costs of:

1.3.6.1. Development of the design solutions specified in the design assignment in several versions, with the exception of variant studies to select the optimal design solutions.

1.3.6.2. Development of solutions for the monumental and decorative design of enterprises, buildings and structures.

1.3.6.3. Making changes to the design and working documentation (with the exception of correcting errors made by the design organization).

1.3.6.4. Development of detailed drawings of metal structures (KMD) and industrial pipelines of factory production.

1.3.6.5. Carrying out surveys and measuring work at facilities subject to reconstruction, expansion and technical re-equipment.

1.3.6.6. Development of design documentation for custom-made equipment, in addition to the preparation of initial requirements for the design of this equipment.

1.3.6.7. Business trips. The base prices of the Guides do not take into account the costs of business trips, including the costs of administrative personnel, if the business trips of this personnel are directly related to the design of the facility.

1.3.6.8. Development of projects for the production of works (PPR).

1.3.6.9. Development of working documentation for the construction of temporary buildings and structures for the needs of construction organizations.

1.3.6.11. Research and experimental work.

1.3.6.12. Development of automated enterprise management systems (APCS) and automated process control systems (APCS).

1.3.6.13. Development of the section "Measures for civil defense and measures to prevent natural and man-made emergencies". The base price for the development of the specified section is determined by the relevant Directory.

1.3.6.14. Performance of work on the assessment of the impact of the capital construction object on the environment (EIA).

1.4. The distribution of the base price for the development of design and working documentation is carried out, as a rule, in accordance with the indicators given in Table 1, and can be specified by agreement between the contractor and the customer.

Table 1

Types of documentation Percentage of base price
Project documentation Working documentation 40 60
TOTAL 100

1.6. When performing design work, in a reduced composition of sections and volumes of work as provided for by the current regulatory documents, their price, regardless of the methods of its calculation, is determined by the prices for the development of design and working documentation using a reduction factor, the amount of which is set by the contractor in agreement with the customer, in accordance with the complexity of the work and the relative cost of developing sections of the design and working documentation.

1.7. When determining the initial (maximum) price of the contract for the performance of design work to their value determined at the time of the competition (auction), it is recommended to use the deflator index established by the Ministry of Economic Development of Russia in accordance with paragraph 5 of the Rules for the development of a forecast for the socio-economic development of the Russian Federation, approved by Decree of the Government of the Russian Federation of July 22, 2009 N 596 (Collected Legislation of the Russian Federation, July 27, 2009, N 30, Article 3833), effective in the middle of the standard design period.

1.8. When using the Handbooks, it should be taken into account that the Handbooks present the recommended relative costs for the development of sections of design and working documentation (as a percentage of the base price), which can be specified for divisions (departments) of the design organization, when designing a specific object, within a certain total design cost, depending on the complexity of the work performed.

II. PROCEDURE FOR APPLICATION OF DIRECTORIES WHEN DETERMINING BASE PRICES FOR PROJECT WORKS

2.1. The procedure for determining the base price depending on the natural indicators of design objects.

2.1.1. The base price for the development of design and working documentation is determined by the formula:

C = (a + bx) x K_i ,

"a" and "b" - constant values ​​for a certain interval of the main indicator of the designed object, in thousand rubles;

x - the main indicator of the designed object;

K_i - coefficient reflecting inflationary processes in the design at the time of determining the price of design work for the construction of the facility.

2.1.2. When applying the Handbooks, it should be taken into account that the prices of the Handbooks for the development of design and working documentation for enterprises, workshops, buildings and structures take into account the cost of designing all on-site engineering networks, communications, structures and devices (electricity supply, water supply, sewerage, heat supply, etc.), including connection workshops, buildings and structures for them, as well as a scheme for the planning organization of a land plot (master plan and landscaping) within the construction site.

If the price in the Directory is set for the development of design and working documentation for the main production (excluding auxiliary, as well as site engineering networks and structures), the total design cost is determined by a set of cost indicators for designing the main and auxiliary facilities.

The cost of designing capital construction projects does not take into account the cost of designing engineering networks and communications outside the construction site.

2.1.3. If the projected object has a value of the main indicator less than the minimum or more than the maximum indicators given in the price tables of the Handbooks, the price for the development of design and working documentation is determined by extrapolation in accordance with the formula given in Appendixes No. 1 and No. 2 to these Guidelines. This provision also applies to positions when in the price table before the minimum and after the maximum are the words "before" and "above", respectively. In cases where the accepted indicator is less than half of the minimum or more than twice the maximum indicator given in the table, the base price of design work is determined in the manner prescribed by paragraph 2.1.4 of these Guidelines.

2.1.4. The price for the development of design and working documentation for the construction of facilities for which prices are not given in the Directories and cannot be accepted by analogy is determined by cost calculation in accordance with costing (Form 3P).

2.2. The procedure for determining the base price of the total cost of construction.

2.2.1. The base price for the development of design and working documentation is determined from the total cost of construction of the entire complex of buildings (structures) or an object, determined according to the summary estimate calculation of the cost of construction, depending on the categories of complexity of design objects.

2.2.2. The cost of construction can be determined:

With the use of analogue objects, taking into account their comparability;

According to the aggregated indicators of the estimated cost per 1 sq. m of total area, 1 cu. m of the volume of the building, 1 m (km) of the route, 1 ha of building, per unit of power, productivity, etc.;

By type or complex of works.

2.2.3. The price for the development of design and working documentation is determined according to the tables of the Handbooks corresponding to the functional purpose of capital construction projects.

2.2.4. The base price of project documentation is determined by the formula:

C - base price of design and working documentation in current prices;

C_01 - base price of design and working documentation as of 01.01.2001;

C_str.01 - construction cost as of 01.01.2001;

alpha - percentage of the base price of the total cost of construction in 2001 prices (table of the Directory);

K_i - coefficient reflecting inflationary processes in the design at the time of determining the price of design work.

To recalculate the cost of construction of objects from the price level as of 01/01/2000 to the price level as of 01/01/2001, a coefficient equal to 1.25 is taken.

2.2.5. When the projected object has a construction cost value that is between the indicators given in the table, the base price for the development of project documentation is determined by interpolation. If the cost of building an object is less or more than the extreme cost indicators given in the price table, the base price of the design work is accepted in the amounts established for the extreme indicators without extrapolation in the direction of decrease or increase.

2.2.6. In the event that the volume of construction and installation work on the construction site is less than 60% of the total cost of construction, the following coefficients are applied to the prices for design work:

up to 50% - 0.95;

2.2.7. If the contract for the performance of design work provides for the possibility of clarifying the cost of design, then such clarification is recommended to be carried out based on the cost of construction determined as a result of the design.

2.2.8. When determining the base price, coefficients that take into account complicating factors (clauses 3.3, 3.7 and 3.8 of these Guidelines) are not applied.

III. PROCEDURE FOR DETERMINING THE COST OF DESIGN WORKS, TAKING INTO ACCOUNT ADDITIONAL FACTORS AFFECTING THE LABOR OUTPUT OF DESIGN

3.1. The price for the development of design and working documentation using the mock-up design method is determined at the prices of the Handbooks using multiplying factors. If there are no established multipliers in the Handbooks, the price for the development of project documentation by the specified method is determined by applying the coefficients to the base price: project documentation - 1.05; working documentation - 1.1.

3.2. The binding price of standard or reusable design documentation, without making changes to the above-ground part of the building, is determined by the prices of the Reference Books using coefficients from 0.2 to 0.35. In this case, the minimum size of the coefficient is accepted when linking the object without making any changes to the aboveground and underground parts of the building. The price of binding standard or reusable project documentation with changes to it in the underground and aboveground parts is determined at the prices of the Reference Books using a general coefficient of up to 0.8, depending on the complexity of the work. The approximate scope of work on the development of individual elements of buildings and structures as a percentage of the design cost is given in Appendix No. 3 to these Guidelines.

3.3. The price for the development of design and working documentation for the construction of unique objects is determined at the prices of the Directories using a multiplying factor of up to 1.5, with the exception of the Directories, which establish a special procedure for calculating the price of these objects.

3.4. The price for the development of design and working documentation for the reconstruction of existing enterprises, workshops, buildings and structures is determined at the prices of Reference books of basic prices for design work for construction.

At the same time, when determining the cost of design work based on the value of the main natural indicator of the projected object, which should be achieved as a result of its reconstruction, technical re-equipment - using a coefficient of up to 1.5 to the prices of the Reference books. When determining the cost of design work from the cost of reconstruction - up to 1.3.

For especially dangerous, technically complex and unique capital construction projects - up to 2.0 and 1.7, respectively.

The size of the coefficient is set by the design organization in agreement with the customer.

3.5. The price for the development of design (working) documentation for the overhaul of facilities is determined according to the relevant reference books of basic prices.

3.6. When compiling local estimates using the resource method, in the absence of a centralized data bank on the current cost of resources in the construction region, a multiplying factor of 1.1 is applied to the cost of developing estimate documentation.

3.7. The price for the development of design and working documentation for the construction of enterprises, buildings and structures in difficult conditions is determined at the prices of the Reference books, applying the following coefficients to the cost of design work, for the development of which special requirements are established by the relevant regulatory documents:

Factors complicating design Odds
Permafrost, subsidence, swelling soils; karst and landslide phenomena; location of the construction site above mine workings, in flooded areas, etc. 1,15
Seismicity 7 points 1,15
Seismicity 8 points 1,20
Seismicity 9 points 1,30

If there are two or more complicating factors, coefficients are applied for each factor.

3.8. The price of designing enterprises, buildings and structures with the installation of imported main technological equipment used by the design organization for the first time is determined by the prices of the Reference Books; at the same time, a coefficient of up to 1.3 is applied to the cost of types of design work, the development of which is complicated due to the use of the specified equipment, as agreed with the customer.

3.9. The costs of design organizations related to their performance of the functions of the general designer and supervision of design work transferred to subcontracts are determined in the amount of up to 2% of the price for the development of design and working documentation transferred to subcontracted design organizations, and are paid additionally.

3.10. The prices of the Handbooks take into account the cost of 4 copies of design and working documentation transferred to the customer. The cost of copies of design products issued at the request of the customer in excess of the specified quantity is determined in addition to the base price.

3.11. When determining the base design price according to the Reference books of basic prices for design work for construction, in the event of a reduction, at the request of the customer, established in the design assignment, design time compared to the standard, it is recommended to apply the following multiplying factors:

with a reduction in the term by 1.2 times - up to 1.1;

1.4 times - up to 1.2;

3.12. Price application guidelines and correction factors given in one Handbook are not allowed to be used when determining the cost of design work according to other Handbooks.

3.13. The price for the development of design and working documentation for the construction of facilities abroad is determined taking into account complicating factors:

N p / p Complicating factors Ratios to development cost
project documentation working documentation
1 2 3 4
1. Translation of text materials of technical documentation, inscriptions on drawings into a foreign language 1,1 1,05
2. Translation of materials of a foreign customer into Russian 1,03 1,03
3. Double checking of calculations, drawings and specifications, calculations of the scope of work, estimate documentation and other design materials, making duplicate copies of cripples, increased requirements for the design and packaging of project documentation 1,2 1,1
4. Other factors affecting the increase in the complexity of design work:
4.1 Current frequency and voltage, the difference in the permissible range of fluctuations in current frequency, different from the Russian Federation (to the cost of designing electrical equipment, power supply, low currents, and, if necessary, other sections) 1,1 1,05
4.2 Dry or humid tropical climate 1,15 1,1
4.3 When the design organization uses for the first time equipment and materials purchased in the customer's countries or supplied from other countries (according to clause 3.8 of these Guidelines) 1,3 1,3
4.4 The application of foreign norms and standards for materials and equipment, the performance of structural calculations on them, etc., specified by the customer in the building for design 1,15 1,2
4.5 Additional requirements for design and working documentation for the construction of facilities on a contract basis, including the preparation of specifications for equipment and materials for temporary import 1,1 1,1

Note - Increasing factors are applied to the cost of design documentation sections or their parts, the development of which becomes more complicated.

3.14. When determining the cost of design work at the prices of the Reference Books, in the presence of several complicating factors and, in connection with this, several coefficients greater than one are used, the total multiplying coefficient is determined by summing their fractional parts and one. When determining the cost of design work using several factors less than one, the overall reduction factor is determined by multiplying them.

When determining the cost of design work at the prices of the Reference Books, the pricing coefficients are multiplied. The pricing factors include the distribution coefficients of the base price for the development of design and working documentation, types of capital construction objects, reconstruction, as well as the coefficients established in the Reference books of basic prices for design work for construction.

3.15. Costs of design organizations located in areas where, in accordance with applicable law, payments are made due to regional regulation of wages, incl. payments according to district coefficients, as well as wage bonuses for continuous work experience and other benefits provided for by legislation in the regions of the Far North and areas equivalent to them, are additionally determined by introducing multiplying coefficients to the base price total, established on the basis of the relevant substantiating calculations performed by the design organization itself.

If the power indicator of the object is less than the tabular indicator, the base price of its design is determined by the formula:

a, b - constant values ​​taken according to the table of the maximum value of the indicator;

X_set - indicator of the designed object.

In the case when only the value "a" is given in the table, and the projected object has an indicator value that does not match those given in the table, the base price of its design is determined by interpolation or extrapolation; when extrapolating upwards or downwards, the value of the correction to the price is reduced by 40% (when calculating the value of the correction, a reduction factor K = 0.6 is introduced).

Appendix No. 2
to the Guidelines
on the use of handbooks
base prices for project
work in construction

EXAMPLES OF DETERMINING THE BASIC PRICE OF DESIGNING OBJECTS, INDICATORS OF WHICH ARE HIGHER, LOWER OR ARE BETWEEN THE INDICATORS GIVEN IN THE TABLES OF THE DIRECTORY<*>

<*>Table indicators are accepted conditionally.

Example 1. In the case when the table of the Base Price Reference contains the values ​​"a" and "b"

N p / p
a b
1 2 3 4 5
19 Sewage sludge incineration facilities with capacity, thousand m3/year:
from 25 to 60 1 thousand m3/year 66,5 1,2

1.1. It is required to determine the base price for the design of sewage sludge incineration facilities with a capacity of 15 thousand m3/year. The base price is determined by the formula:

a and b are constant values ​​taken according to the table of the maximum value of the indicator;

X_max - the maximum value given in the table;

X_zad - a given indicator of the designed object.

Calculation example:

66.5 + 1.2 x (0.4 x 60 + 0.6 x 80) = 152.9 thousand rubles.

Example 2. In the case when only the value "a" is given in the table of the Base Price Reference

In the Reference book of basic prices for design work, a table is given:

N p / p Name of the design object Unit of measurement of the main indicator of the object Constant values ​​of the base price for the development of design and working documentation, thousand rubles.
a b
1 2 3 4 5
Wash water treatment facilities, capacity, m3/day.
65 160 1 m3/day 4,4 -
66 500 -"- 5,5 -
.. ............... ........ .......... ...
.. ............... ........ .......... ...
72 40000 -"- 219,4 -
73 80000 -"- 369,1 -

2.1. It is required to determine the base price for designing a wash water treatment facility with a capacity of 100 m3/day.

1.1. Guidelines for the use of reference books of basic prices for design work in construction (hereinafter referred to as the Guidelines) are intended to determine the cost of developing design and working documentation for the construction of new buildings and structures, their reconstruction, expansion and technical re-equipment (hereinafter referred to as the construction of facilities), determined from application of reference books of basic prices for design work in construction.

1.2. The provisions given in the Guidelines apply to all Reference books of basic prices for design work in construction (hereinafter referred to as the Reference books) entered in the federal register of estimated standards to be used when determining the estimated cost of capital construction projects as state estimated standards.

1.3.1. The base prices of the Reference books are set depending on the natural indicators of the design objects (capacity, length, capacity, area, etc.) or on the total cost of construction.

1.3.2. The prices given in the Handbooks are set in accordance with the composition and requirements for the content of sections of project documentation for the construction of enterprises, buildings, structures, provided for by Decree of the Government of the Russian Federation of February 16, 2008 N 87 "On the composition of sections of project documentation and requirements for their content "(Collected Legislation of the Russian Federation, 2008, N 8, Art. 744).

1.3.3. The Handbooks provide prices for individual design of capital construction objects of buildings and structures using drawings of standard (reusable) products and assemblies for individual elements of building structures.

1.3.4. The prices in the Handbooks take into account the costs of developing design and working documentation, attributable without value added tax.

1.3.5.2. Participation of the design organization together with the customer in coordinating the finished project documentation with state bodies and local governments.

1.3.6.1. Development of the design solutions specified in the design assignment in several versions, with the exception of variant studies to select the optimal design solutions.

1.3.6.6. Development of design documentation for custom-made equipment, in addition to the preparation of initial requirements for the design of this equipment.

1.3.6.7. Business trips. The base prices of the Guides do not take into account the costs of business trips, including the costs of administrative personnel, if the business trips of this personnel are directly related to the design of the facility.

1.3.6.12. Development of automated enterprise management systems (APCS) and automated process control systems (APCS).

1.3.6.13. Development of the section "Measures for civil defense and measures to prevent natural and man-made emergencies". The base price for the development of the specified section is determined by the relevant Directory.

1.4. The distribution of the base price for the development of design and working documentation is carried out, as a rule, in accordance with the indicators given in Table 1, and can be specified by agreement between the contractor and the customer.

1.5. If the design assignment provides for the simultaneous development of design documentation and partial development of working documentation, then the total percentage of the base price is determined by agreement between the construction customer and the design organization, depending on the architectural, functional, technological, structural and engineering solutions contained in the design documentation , as well as their level of detail.

1.6. When performing design work, in a reduced composition of sections and volumes of work as provided for by the current regulatory documents, their price, regardless of the methods of its calculation, is determined by the prices for the development of design and working documentation using a reduction factor, the amount of which is set by the contractor in agreement with the customer, in accordance with the complexity of the work and the relative cost of developing sections of the design and working documentation.

1.7. When determining the initial (maximum) price of the contract for the performance of design work to their value determined at the time of the competition (auction), it is recommended to use the deflator index established by the Ministry of Economic Development of Russia in accordance with paragraph 5 of the Rules for the development of a forecast for the socio-economic development of the Russian Federation, approved by Decree of the Government of the Russian Federation of July 22, 2009 N 596 (Collected Legislation of the Russian Federation, July 27, 2009, N 30, Article 3833), effective in the middle of the standard design period.

1.8. When using the Handbooks, it should be taken into account that the Handbooks present the recommended relative costs for the development of sections of design and working documentation (as a percentage of the base price), which can be specified for divisions (departments) of the design organization, when designing a specific object, within a certain total design cost, depending on the complexity of the work performed.

2.1.3. If the projected object has a value of the main indicator less than the minimum or more than the maximum indicators given in the price tables of the Handbooks, the price for the development of design and working documentation is determined by extrapolation in accordance with the formula given in Appendixes No. 1 and No. 2 to these Guidelines. This provision also applies to positions when in the price table before the minimum and after the maximum are the words "before" and "above", respectively. In cases where the accepted indicator is less than half of the minimum or more than twice the maximum indicator given in the table, the base price of design work is determined in the manner prescribed by paragraph 2.1.4 of these Guidelines.

ON APPROVAL OF METHODOLOGICAL INSTRUCTIONS

WORKS IN CONSTRUCTION

In accordance with the Regulations on the Ministry of Regional Development of the Russian Federation, approved by Decree of the Government of the Russian Federation of January 26, 2005 N 40 (Collected Legislation of the Russian Federation, 2005, N 5, Art. 390; N 13, Art. 1169; 2006, N 6 , item 712; N 18, item 2002; 2007, N 45, item 5488; 2008, N 22, item 2582, N 42, item 4825, N 46, item 5337; 2009, N 3, item 378, N 6, item 738; N 14, item 1669; N 38, item 4497), Order of the Ministry of Regional Development of the Russian Federation of April 11, 2008 N 44 "On approval of the Procedure for the development and approval of standards in the field of budget regulation and pricing in the field of urban planning" (registered by the Ministry of Justice of the Russian Federation on May 12, 2008, registration N 11661, Bulletin of Normative Acts of Federal Executive Authorities, 2008, N 22) and by Order of the Ministry of Regional Development of the Russian Federation of August 20, 2009 N 353 "On approval of the qualification of estimated standards to be applied when determining the estimated cost of capital construction projects, the construction of which is financed with the involvement of federal budget funds" (registered by the Ministry of Justice of the Russian Federation on 02.10.2009, registration N 14940, Bulletin of normative acts of federal executive bodies, 2009, N 42) I order:

1. Approve as a state estimate standard the attached Guidelines for the use of reference books of basic prices for design work in construction.

2. The Department for Regulation of Urban Development (I.V. Ponomarev), within 10 days from the date of signing, send this Order for state registration to the Ministry of Justice of the Russian Federation.

3. The control of the execution of this Order shall be entrusted to the Deputy Minister of Regional Development of the Russian Federation S.I. Kruglik.

And about. Minister

V.A.TOKAREV

Approved

Order of the Ministry

regional development

Russian Federation

dated December 29, 2009 No. 620

METHODOLOGICAL INSTRUCTIONS

ON THE APPLICATION OF DIRECTORIES OF BASE PRICES FOR PROJECT

WORKS IN CONSTRUCTION

I. GENERAL PROVISIONS

1.1. Guidelines for the use of reference books of basic prices for design work in construction (hereinafter referred to as the Guidelines) are intended to determine the cost of developing design and working documentation for the construction of new buildings and structures, their reconstruction, expansion and technical re-equipment (hereinafter referred to as the construction of facilities), determined from application of reference books of basic prices for design work in construction.

1.2. The provisions given in the Guidelines apply to all Reference books of basic prices for design work in construction (hereinafter referred to as the Reference books) entered in the federal register of estimated standards to be used when determining the estimated cost of capital construction projects as state estimated standards.

1.3. When using the Handbooks, the following should be taken into account:

1.3.1. The base prices of the Reference books are set depending on the natural indicators of the design objects (capacity, length, capacity, area, etc.) or on the total cost of construction.

1.3.2. The prices given in the Handbooks are set in accordance with the composition and requirements for the content of sections of project documentation for the construction of enterprises, buildings, structures, provided for by Decree of the Government of the Russian Federation of February 16, 2008 N 87 "On the composition of sections of project documentation and requirements for their content "(Collected Legislation of the Russian Federation, 2008, N 8, Art. 744).

1.3.3. The Handbooks provide prices for individual design of capital construction objects of buildings and structures using drawings of standard (reusable) products and assemblies for individual elements of building structures.

1.3.4. The prices in the Handbooks take into account the costs of developing design and working documentation, attributable without value added tax.

1.3.5. The prices of the Handbooks include the following works and services:

1.3.5.1. Production of demonstration materials (except for demonstration layouts).

1.3.5.2. Participation of the design organization together with the customer in coordinating the finished project documentation with state bodies and local governments.

1.3.5.3. Protection of project documentation in expert and approving instances.

1.3.6. The prices of the Handbooks for the development of design and working documentation do not include the costs of:

1.3.6.1. Development of the design solutions specified in the design assignment in several versions, with the exception of variant studies to select the optimal design solutions.

1.3.6.2. Development of solutions for the monumental and decorative design of enterprises, buildings and structures.

1.3.6.3. Making changes to the design and working documentation (with the exception of correcting errors made by the design organization).

1.3.6.4. Development of detailed drawings of metal structures (KMD) and industrial pipelines of factory production.

1.3.6.5. Carrying out surveys and measuring work at facilities subject to reconstruction, expansion and technical re-equipment.

1.3.6.6. Development of design documentation for custom-made equipment, in addition to the preparation of initial requirements for the design of this equipment.

1.3.6.7. Business trips. The base prices of the Guides do not take into account the costs of business trips, including the costs of administrative personnel, if the business trips of this personnel are directly related to the design of the facility.

1.3.6.8. Development of projects for the production of works (PPR).

1.3.6.9. Development of working documentation for the construction of temporary buildings and structures for the needs of construction organizations.

1.3.6.11. Research and experimental work.

1.3.6.12. Development of automated enterprise management systems (APCS) and automated process control systems (APCS).

1.3.6.13. Development of the section "Measures for civil defense and measures to prevent natural and man-made emergencies". The base price for the development of the specified section is determined by the relevant Directory.

1.3.6.14. Performance of work on the assessment of the impact of the capital construction object on the environment (EIA).

1.4. The distribution of the base price for the development of design and working documentation is carried out, as a rule, in accordance with the indicators given in Table 1, and can be specified by agreement between the contractor and the customer.

Table 1

┌─────────────────────────────────────────────────── ─────┐ │ Types of documentation │ Percentage of base price │ ├──────────────────────────┼───────── ────────────────────┤ │Project documentation │ 40 │ │Working documentation │ 60 │ ├────────────────── ──────────┼────────────────────────────┤ │ TOTAL│ 100 │ └────── ──────────────────────┴────────────────────────────

1.5. If the design assignment provides for the simultaneous development of design documentation and partial development of working documentation, then the total percentage of the base price is determined by agreement between the construction customer and the design organization, depending on the architectural, functional, technological, structural and engineering solutions contained in the design documentation , as well as their level of detail.

1.6. When performing design work, in a reduced composition of sections and volumes of work as provided for by the current regulatory documents, their price, regardless of the methods of its calculation, is determined by the prices for the development of design and working documentation using a reduction factor, the amount of which is set by the contractor in agreement with the customer, in accordance with the complexity of the work and the relative cost of developing sections of the design and working documentation.

1.7. When determining the initial (maximum) price of the contract for the performance of design work to their value determined at the time of the competition (auction), it is recommended to use the deflator index established by the Ministry of Economic Development of Russia in accordance with paragraph 5 of the Rules for the development of a forecast for the socio-economic development of the Russian Federation, approved by Decree of the Government of the Russian Federation of July 22, 2009 N 596 (Collected Legislation of the Russian Federation, July 27, 2009, N 30, Article 3833), effective in the middle of the standard design period.

1.8. When using the Handbooks, it should be taken into account that the Handbooks present the recommended relative costs for the development of sections of design and working documentation (as a percentage of the base price), which can be specified for divisions (departments) of the design organization, when designing a specific object, within a certain total design cost, depending on the complexity of the work performed.

II. PROCEDURE FOR APPLICATION OF DIRECTORIES WHEN DETERMINING

BASE PRICES FOR PROJECT WORKS

2.1. The procedure for determining the base price depending on the natural indicators of design objects.

2.1.1. The base price for the development of design and working documentation is determined by the formula:

C = (a + bx) x K , i x - the main indicator of the designed object; K - coefficient reflecting inflationary processes in the design at the i moment of determining the price of design work for the construction of the facility.

2.1.2. When applying the Handbooks, it should be taken into account that the prices of the Handbooks for the development of design and working documentation for enterprises, workshops, buildings and structures take into account the cost of designing all on-site engineering networks, communications, structures and devices (electricity supply, water supply, sewerage, heat supply, etc.), including connection workshops, buildings and structures for them, as well as a scheme for the planning organization of a land plot (master plan and landscaping) within the construction site.

If the price in the Directory is set for the development of design and working documentation for the main production (excluding auxiliary, as well as site engineering networks and structures), the total design cost is determined by a set of cost indicators for designing the main and auxiliary facilities.

The cost of designing capital construction projects does not take into account the cost of designing engineering networks and communications outside the construction site.

2.1.3. If the projected object has a value of the main indicator less than the minimum or more than the maximum indicators given in the price tables of the Handbooks, the price for the development of design and working documentation is determined by extrapolation in accordance with the formula given in Appendixes No. 1 and No. 2 to these Guidelines. This provision also applies to positions when in the price table before the minimum and after the maximum are the words "before" and "above", respectively. In cases where the accepted indicator is less than half of the minimum or more than twice the maximum indicator given in the table, the base price of design work is determined in the manner prescribed by paragraph 2.1.4 of these Guidelines.

2.1.4. The price for the development of design and working documentation for the construction of facilities for which prices are not given in the Directories and cannot be accepted by analogy is determined by cost calculation in accordance with costing (Form 3P).

2.2. The procedure for determining the base price of the total cost of construction.

2.2.1. The base price for the development of design and working documentation is determined from the total cost of construction of the entire complex of buildings (structures) or an object, determined according to the summary estimate calculation of the cost of construction, depending on the categories of complexity of design objects.

2.2.2. The cost of construction can be determined:

With the use of analogue objects, taking into account their comparability;

According to the aggregated indicators of the estimated cost per 1 sq. m of total area, 1 cu. m of the volume of the building, 1 m (km) of the route, 1 ha of building, per unit of power, productivity, etc.;

By type or complex of works.

2.2.3. The price for the development of design and working documentation is determined according to the tables of the Handbooks corresponding to the functional purpose of capital construction projects.

2.2.4. The base price of project documentation is determined by the formula:

C x alpha p.01 C = C x K = ----------------- x K , 01 i 100 i where C is the base price of design and working documentation in current prices; C - base price of design and working documentation as of 01.01.2001; 01 C - construction cost as of 01.01.2001; p.01 alpha - percentage of the base price of the total cost of construction in 2001 prices (table of the Directory); K - coefficient reflecting inflationary processes in i design at the time of determining the price of design work.

To recalculate the cost of construction of objects from the price level as of 01/01/2000 to the price level as of 01/01/2001, a coefficient equal to 1.25 is taken.

2.2.5. When the projected object has a construction cost value that is between the indicators given in the table, the base price for the development of project documentation is determined by interpolation. If the cost of building an object is less or more than the extreme cost indicators given in the price table, the base price of the design work is accepted in the amounts established for the extreme indicators without extrapolation in the direction of decrease or increase.

2.2.6. In the event that the volume of construction and installation work on the construction site is less than 60% of the total cost of construction, the following coefficients are applied to the prices for design work:

Up to 50% - 0.95;

Up to 40% - 0.9;

Up to 30% - 0.8;

Up to 20% - 0.7.

2.2.7. If the contract for the performance of design work provides for the possibility of clarifying the cost of design, then such clarification is recommended to be carried out based on the cost of construction determined as a result of the design.

2.2.8. When determining the base price, coefficients that take into account complicating factors (clauses 3.3, 3.7 and 3.8 of these Guidelines) are not applied.

III. PROCEDURE FOR DETERMINING THE COST OF PROJECT

WORKS WITH ADDITIONAL FACTORS AFFECTING

ON THE LABOR INTENSITY OF DESIGN

3.1. The price for the development of design and working documentation using the mock-up design method is determined at the prices of the Handbooks using multiplying factors. If there are no established multipliers in the Handbooks, the price for the development of project documentation by the specified method is determined by applying the coefficients to the base price: project documentation - 1.05; working documentation - 1.1.

3.2. The binding price of standard or reusable design documentation, without making changes to the above-ground part of the building, is determined by the prices of the Reference Books using coefficients from 0.2 to 0.35. In this case, the minimum size of the coefficient is accepted when linking the object without making any changes to the aboveground and underground parts of the building. The price of binding standard or reusable project documentation with changes to it in the underground and aboveground parts is determined at the prices of the Reference Books using a general coefficient of up to 0.8, depending on the complexity of the work. The approximate scope of work on the development of individual elements of buildings and structures as a percentage of the design cost is given in Appendix No. 3 to these Guidelines.

3.3. The price for the development of design and working documentation for the construction of unique objects is determined at the prices of the Directories using a multiplying factor of up to 1.5, with the exception of the Directories, which establish a special procedure for calculating the price of these objects.

3.4. The price for the development of design and working documentation for the reconstruction of existing enterprises, workshops, buildings and structures is determined at the prices of Reference books of basic prices for design work for construction.

At the same time, when determining the cost of design work based on the value of the main natural indicator of the projected object, which should be achieved as a result of its reconstruction, technical re-equipment - using a coefficient of up to 1.5 to the prices of the Reference books. When determining the cost of design work from the cost of reconstruction - up to 1.3.

For especially dangerous, technically complex and unique capital construction projects - up to 2.0 and 1.7, respectively.

The size of the coefficient is set by the design organization in agreement with the customer.

3.5. The price for the development of design (working) documentation for the overhaul of facilities is determined according to the relevant reference books of basic prices.

3.6. When compiling local estimates using the resource method, in the absence of a centralized data bank on the current cost of resources in the construction region, a multiplying factor of 1.1 is applied to the cost of developing estimate documentation.

3.7. The price for the development of design and working documentation for the construction of enterprises, buildings and structures in difficult conditions is determined at the prices of the Reference books, applying the following coefficients to the cost of design work, for the development of which special requirements are established by the relevant regulatory documents:

Factors complicating Design factors Permafrost, subsidence, swelling soils; karst and landslide phenomena; location of the construction site above mine workings, in flooded areas, etc. 1.15 Seismicity 7 points 1.15 Seismicity 8 points 1.20 Seismicity 9 points 1.30

If there are two or more complicating factors, coefficients are applied for each factor.

3.8. The price of designing enterprises, buildings and structures with the installation of imported main technological equipment used by the design organization for the first time is determined by the prices of the Reference Books; at the same time, a coefficient of up to 1.3 is applied to the cost of types of design work, the development of which is complicated due to the use of the specified equipment, as agreed with the customer.

3.9. The costs of design organizations related to their performance of the functions of the general designer and supervision of design work transferred to subcontracts are determined in the amount of up to 2% of the price for the development of design and working documentation transferred to subcontracted design organizations, and are paid additionally.

3.10. The prices of the Handbooks take into account the cost of 4 copies of design and working documentation transferred to the customer. The cost of copies of design products issued at the request of the customer in excess of the specified quantity is determined in addition to the base price.

3.11. When determining the base design price according to the Reference books of basic prices for design work for construction, in the event of a reduction, at the request of the customer, established in the design assignment, design time compared to the standard, it is recommended to apply the following multiplying factors:

With a reduction in the term by 1.2 times - up to 1.1; 1.4 times - up to 1.2; 2 or more times - up to 1.4.

3.12. Price application guidelines and correction factors given in one Handbook are not allowed to be used when determining the cost of design work according to other Handbooks.

3.13. The price for the development of design and working documentation for the construction of facilities abroad is determined taking into account complicating factors:

┌────┬────────────────────────────────────────┬──── N ──────────┬─────────────┤ │ │ │ design │ working │ │ │ │ documentation │documentation│ ├────┼─────── ──────────────────────────────────────────────────┼ ─────────────┤ │ 1 │ 2 │ 3 │ 4 │ ├────┼─────────────────────── 1. │Translation of technical text materials│ 1.1 │ 1.05 │ │ │documentation, inscriptions on drawings into │ │ │ │ │foreign language │ │ │ ──────────────────────────────────────────────────── ──────┤ │ 2. │Translation of foreign materials│ 1.03 │ 1.03 │ │ │of the customer into Russian │ │ │ ├─────┼────────────── ──────────────────────────────────────────────────── ──────┤ │ 3. │Double check of calculations, drawings and │ 1.2 │ 1.1 │ │ │ specifications, calculations of the amount of work, │ │ │ │ │ estimate documentation and other design materials , production of duplicates│ │ │ │ │cripples, increased requirements for ──────────────────────────────────────────────────── ─────┤ │ 4. │Other factors affecting the increase│ │ │ │ │labor intensity of design work: │ │ │ │4.1 within the frequency fluctuations │ │ │ │ │ current, different from the Russian Federation │ │ │ │ │ │ other sections) │ │ │ │ 4.2 │ Dry or humid tropical climate │ 1.15 │ 1.1 │ │ 4.3 │ When used by the design organization│ 1.3 │ 1.3 │ │ │ │purchased in the countries of the customer or │ │ │ │ │supplied from other countries (according to paragraph │ │ │ │ │3.8 of these Guidelines) │ │ │ │4.4 │Application of foreign norms and standards│ 1.15 │ 1.2 │ │ │on materials and equipment, performance│ │ │ │ │on them of structural calculations and other, │ │ │ │ │specified by the customer in the building on 1 │ 1.1 │ │ │working documentation during construction│ │ │ │ │objects on contractual terms, including │ │ │ │ │preparation of specifications for │ │ │ │ │equipment and materials of temporary │ │ │ │ │import │ └────┴───────────────────────────────────────┴─── ─────────────┴──────────────┘

Note - Increasing factors are applied to the cost of design documentation sections or their parts, the development of which becomes more complicated.

3.14. When determining the cost of design work at the prices of the Reference Books, in the presence of several complicating factors and, in connection with this, several coefficients greater than one are used, the total multiplying coefficient is determined by summing their fractional parts and one. When determining the cost of design work using several factors less than one, the overall reduction factor is determined by multiplying them.

When determining the cost of design work at the prices of the Reference Books, the pricing coefficients are multiplied. The pricing factors include the distribution coefficients of the base price for the development of design and working documentation, types of capital construction objects, reconstruction, as well as the coefficients established in the Reference books of basic prices for design work for construction.

3.15. Costs of design organizations located in areas where, in accordance with applicable law, payments are made due to regional regulation of wages, incl. payments according to district coefficients, as well as wage bonuses for continuous work experience and other benefits provided for by legislation in the regions of the Far North and areas equivalent to them, are additionally determined by introducing multiplying coefficients to the base price total, established on the basis of the relevant substantiating calculations performed by the design organization itself.

Appendix No. 1

to the Guidelines

on the use of handbooks

base prices for project

work in construction

EXTRAPOLATION AND INTERPOLATION

WHEN CALCULATION OF THE PRICE OF DESIGN WORKS

In the case when the projected object has a value of the main indicator less than the minimum or more than the maximum indicator given in the table of the Base Price Directory, the base price of the design is determined by extrapolation; at the same time, the value of the adjustment to the price is reduced by 40%, i.e. when calculating the indicator of the projected object X ass is taken with a coefficient of 0.6.

If the power indicator of the object is less than the tabular indicator, the base price of its design is determined by the formula:

C \u003d a + b x (0.4 x X + 0.6 x X), min set. where a, b are constant values ​​taken according to the table of the minimum value of the indicator; X - the minimum indicator given in the table; min X - indicator of the designed object. ass

If the power indicator of the object is greater than the tabular indicator, the base price of its design is determined by the formula:

C = a + b x (0.4 x X + 0.6 x X), max. where a, b are constant values ​​taken according to the table of the maximum value of the indicator; X - the maximum indicator given in the table; max X - indicator of the designed object. ass

In the case when only the value "a" is given in the table, and the projected object has an indicator value that does not match those given in the table, the base price of its design is determined by interpolation or extrapolation; when extrapolating upwards or downwards, the value of the correction to the price is reduced by 40% (when calculating the value of the correction, a reduction factor K = 0.6 is introduced).


Top